Building Expansion Project

Timetable

check

Evaluated library needs.

 

check

Hired Building Program Planning Consultants.

 

check

With consultants, created building program.

 

check

Put in University Request for Proposal (RFP) for an architectural firm.

 

check

Hired architects.

 

check

Program Confirmation stage: Working with initial building program, architects design initial drafts of floor plans. (Projected due date: July 8, 2003)

 

check

July 31, 2003: Ekstrom Library Expansion Talk and Brown-Bag Lunch.
Have questions about the U of L Libraries' upcoming expansion? Want to learn more about "the box", the cafe, the McConnell Center, study and meeting spaces, stacks, Kersey library's merger to Ekstrom and the Laura Kersey Reading Room? Come learn about Ekstrom Library's new wing with us. Bring your lunch! Thursday, July 31 noon to 1 p.m. in Ekstrom Library, room 254. Part of the U of L Libraries' Collaborative Series. Questions? Contact Mary Barbosa-Jerez, 852-8738, mebarb01@louisville.edu


check August 19, 2003: The Student Government Association sponsored a focus group for students to provide their feedback and ideas on what the new wing should be like.

 

check

RFID Demos: Radio Frequency Identification (electronic barcodes) technology demonstrations. Ekstrom Library, Rm. 254. Please RSVP to Weiling Liu and which demo you wish to attend.
Demo 1 - August 19, 1-3:30pm (RSVP by Aug. 12)
Demo 2 - August 25, 12:30-3pm (RSVP by Aug. 20)

 

check

Library Personnel Forums on the Ekstrom Library Expansion. Two informal forums for library employees interested in an update on the expansion or having questions related to the project.
August 20, 2003 Noon-1pm   Ekstrom Library, Rm 254
August 26, 2003 Noon-1pm   Kornhauser Library History Room

 

check

Schematic stage: Firm up details of floor plans and identify materials. (Projected time: 8 weeks)

 

check

Design Development stage: Address the smaller details of the plan and materials. (Projected time: 16 weeks)

 

check

Groundbreaking: April 12, 2004.

 

check

Construction Documents created, including blueprints and specifications. Completed May 5, 2004.

 

check

Put in RFP for contractors.

 

check

Hired contractors. Completed July 30, 2004.

 

check

Construction. (Projected time: 400 days, beginning August 9.)

 

check

Furnished addition.

 

check

Occupancy: February 2006.

 

 

 